SmartManager administers the following set of variables.

Editable on SmartTransfer Pro

Also viewable on:

  • Console

  • SmartDashboard

Variable name

Description

Example Data

Last Updated Time

When any MES data was last changed

 

Last Updated By

Who changed the MES data last

 

Internal Order Code

The internal order code relating to the project

SO1234

Process Step

The step that the job file represents in the project

2 of 4

Total Parts Required

The number of parts required from the customer

50

Parts Made Per Job

The number of parts a single job file can produce

10

Stock Material Type

The type of material required for the job

Plywood

Job Size X Axis

Job size in X

1000 mm

Job Size Y Axis

Job size in Y

2000 mm

Job Size Z Axis

Job size in Z

12 mm

Stock Material Size

The minimum size of stock material required for the job

1220 x 2440 x 12 mm

Pre Production Notes

Any additional notes that the operator may require prior to running the job. These are notes typically issued by the programmer or manager

Z height datum check is critical.

Top surface is customer facing.

Ensure deburr on lower face.

Clear all swarf between all teeth.

Primary Operator

The name of the operator skilled in this job

Finn

Job Duration

The estimated amount of time that this job file will take to complete

00:15:22

End Effector

Type of end effector used

Spindle

Tool Diameter And Type

The diameter and type of tool used

6 mm upcut spiral

Toolpath Name

Name of toolpath set in CAM stage

Profile cut

XY Datum Position

XY datum position relative to the stock

Bottom right

Z Datum Position

Z datum position relative to the stock

Stock top

Maximum Feed Rate

The maximum feed rate for the job

6,000 mm/min

Maximum Plunge Rate

The maximum plunge rate for the job

750 mm/min

Maximum Spindle Speed

The maximum spindle speed for the job

25,000 RPM

Customer Name

The name of the customer

Yeti Tool

Customer Part Number

The customer's part number

201598

Customer Part Description

The name of the part that the job file belongs to. A part can be made up of multiple job files

X racks

Customer Order Reference

Typically the purchase order number provided by the customer

PO4321

Parts Made So Far

The number of parts completed so far

 

Editable on Console

Also viewable on:

  • SmartDashboard

Variable name

Description

Example Data

Parts Made So Far

The number of parts completed so far

 

Batch Number

A code relating to the batch of items this item belongs to

YT394857

Post Production Notes

Notes added by the operator after job completion

3 tabs broke on part X during final operation

Machine Name

The name of the SmartBench (configurable at machine)

X rack cutter

Machine Location

The position of the machine in the factory (configurable at machine)

Rack cutting room

Viewable on Dashboard

In addition to all of the variables listed above, the Dashboard also displays the following variables:

Variable name

Description

Example Data

Machine Status

The current status of the SmartBench

Idle

Spindle Overload

The peak spindle overload seen during the course of running the job file

20%

Current Job Time

The length of time the current job has been running

1:23:45

Current Job Percentage

Measurement of progress through the job file. This is measured in the number of lines of GCode processed, compared to the total number of GCode lines in the job file. Note that because some GCode lines take longer to effect than others, progress indicated may not correlate exactly with time remaining

99%

Z Lube Hours Since Last Maintenance

Percentage of hours remaining before Z axis needs to be relubricated

30%

Z Lube Hours Before Maintenance Required

Number of hours remaining before Z axis needs to be relubricated

15

Spindle Brush Since Last Maintenance

Percentage of hours remaining before spindle brushes need to be replaced

50%

Spindle Brush Hours Before Maintenance Required

Number of hours remaining before spindle brushes need to be replaced

125

Calibration Since Last Maintenance

Percentage of hours remaining before XY calibration needs to be checked

50%

Calibration Hours Before Maintenance Required

Number of hours remaining before XY calibration needs to be checked

50

Current Job Gcode Line

The last line of GCode to be streamed from the console to the ZHead

342

Actual Job Duration

Total time job has run for after completion

34520

Actual Job Pause Duration

   

SmartBench Version

Version of console software

V1.8.2


< Previous | List | Next >

If this article didn't solve your problem, please submit a support ticket here

Rami

Rami is the author of this solution

Glad we could be helpful. Thanks for the feedback.

Sorry we couldn't be helpful. Your feedback will help us improve this article.

Did you find it helpful?

Yes   No
Updated on Fri, 29 Oct 2021